Chapter 1501:21-22 Inspection of Repairs and Corrections

1501:21-22-01 Inspection procedure.

The chief may make inspections during repair construction as deemed necessary to ensure that the structure is being repaired in compliance with the approved plans and specifications. However, the inspections by the chief do not relieve the owner or the registered professional engineer in charge of the responsibility of providing adequate inspection of the work.

R.C. 119.032 review dates: 03/08/2010 and 03/05/2015
Promulgated Under: 119.03
Statutory Authority: 1521.06
Rule Amplifies: 1521.062
Prior Effective Dates: 12-9-99

1501:21-22-02 Notice, order, and revocation for noncompliance.

If at any time during the progress of the repair construction the chief finds that the work is not being performed in accordance with the approved plans, specifications, and changes, the chief may serve a written notice to that effect to the owner or the owner's representative by registered or certified mail. Such notice shall state the particulars in which the work has not complied with the approved plans, specifications, and or changes. The chief may order the immediate compliance with the approved plans, specifications, and changes. As prescribed by rule 1501:21-23-01 of the Administrative Code, each chiefs order shall inform the affected party of the hearing and appeal provisions of Chapter 119. of the Revised Code.

R.C. 119.032 review dates: 03/08/2010 and 03/05/2015
Promulgated Under: 119.03
Statutory Authority: 1521.06
Rule Amplifies: 1521.062
Prior Effective Dates: 12-9-99; 1-16-05

1501:21-22-03 Approval of construction by the chief.

Upon receipt of the engineer's certification and the as-built plans required in paragraph (C) of rule 1501:21-21-03 of the Administrative Code, the chief shall within thirty days inspect the completed construction. If the chief finds that construction was completed in accordance with the approved plans, specifications, and changes, the chief shall within fourteen days after inspection approve the construction and notify the owner in writing. If the chief finds that construction was not completed in accordance with the approved plans, specifications, and changes, the chief shall notify the owner of the necessary remedial measures within fourteen days after inspection.

R.C. 119.032 review dates: 03/08/2010 and 03/05/2015
Promulgated Under: 119.03
Statutory Authority: 1521.06
Rule Amplifies: 1521.062
Prior Effective Dates: 12-9-99; 1-16-05