Rule 3701:1-44-24 | Effluent monitoring reporting requirements.

 

Each licensee authorized to possess and use source material in uranium milling shall, within sixty days after January first and July first of each year, submit a report to the director using an appropriate method listed in rule 3701:1-44-05 of the Administrative Code. The report must specify the quantity of each of the principal radionuclides released to unrestricted areas in liquid and in gaseous effluents during the previous six months of operation, and such other information as the department may require to estimate maximum potential annual radiation doses to the public resulting from effluent releases. If quantities of radioactive materials released during the reporting period are significantly above the licensee's design objectives previously reviewed as part of the licensing action, the report shall cover this specifically. On the basis of such reports and any additional information the director may obtain from the licensee or others, the director may from time to time require the licensee to take such action as the director deems appropriate.

Last updated November 2, 2022 at 2:16 PM

Supplemental Information

Authorized By: 3748.04
Amplifies: 3748.04
Five Year Review Date: 5/13/2027
Prior Effective Dates: 2/6/2006