3745-104-30 Program three prevention program: pre-startup review.

(A) The owner or operator shall perform a pre-startup safety review for new stationary sources and for modified stationary sources when the modification of the covered process is significant enough to require a change in the process safety information.

(B) The pre-startup safety review shall confirm that prior to the introduction of regulated substances to a process:

(1) Construction and equipment is in accordance with design specifications;

(2) Safety, operating, maintenance, and emergency procedures are in place and are adequate;

(3) For new stationary sources, a process hazard analysis has been performed and recommendations have been resolved or implemented before startup; and modified stationary sources meet the requirements contained in management of change, rule 3745-104-29 of the Administrative Code.

(4) Training of each employee involved in operating a process has been completed.

R.C. 119.032 review dates: 10/23/2009 and 10/23/2014

Promulgated Under: 119.03

Statutory Authority: 3753.02

Rule Amplifies: 3753

Prior Effective Dates: 8/13/99