(A) The owner or operator shall perform a pre-startup safety review for new stationary sources and for modified stationary sources when the modification of the covered process is significant enough to require a change in the process safety information.
(B) The pre-startup safety review shall confirm that prior to the introduction of regulated substances to a process:
(1) Construction and equipment is in accordance with design specifications;
(2) Safety, operating, maintenance, and emergency procedures are in place and are adequate;
(3) For new stationary sources, a process hazard analysis has been performed and recommendations have been resolved or implemented before startup; and modified stationary sources meet the requirements contained in management of change, rule 3745-104-29 of the Administrative Code.
(4) Training of each employee involved in operating a process has been completed.