3745-500-210 Variances for solid waste facilities.

(A) An application for a variance for a solid waste facility shall include the following:

(1) The provision or provisions of the state law for which the variance is requested.

(2) Information regarding the reason and justification for the variance.

(3) Any other pertinent data regarding the application required by the director.

(4) A certification statement and signature in accordance with rule 3745-500-50 of the Administrative Code.

(B) In accordance with division (S)(1) of section 3745.11 of the Revised Code, the nonrefundable fee shall be paid at the time the application for a variance is submitted. If the application for a variance is part of an application for a permit to install, the variance application fee shall be paid in addition to the permit to install application fee.

(C) The director shall issue, renew, or deny an application for a variance or renewal of a variance for a solid waste facility not later than six months after the date upon which the director receives a complete application with all pertinent information and data required unless the application for a variance is part of an application for a permit to install. If an application for a variance is part of an application for a permit to install, the director shall issue, renew, or deny an application for a variance or renewal of a variance concurrent with a final or proposed action on the permit to install application.

(D) When issuing a variance for a solid waste facility, the director shall act in accordance with Chapters 119., 3734., and 3745. of the Revised Code, as applicable.

Effective: 04/02/2012
R.C. 119.032 review dates: 04/02/2017
Promulgated Under: 119.03
Statutory Authority: 3734.02
Rule Amplifies: 3734.02