3745-54-54 Amendment of contingency plan.

(A) The contingency plan shall be reviewed, and immediately amended if necessary, whenever any of the following:

(1) The facility's Ohio hazardous waste permit is modified.

(2) The contingency plan fails in an emergency .

(3) The facility changes - in its design, construction, operation, maintenance, or other circumstances - in a way that materially increases the potential for fires, explosions, or releases of hazardous waste or hazardous waste constituents, or changes the response necessary in an emergency .

(4) The list of emergency coordinators changes .

(5) The list of emergency equipment changes .

(6) Required by the director.

(B) A change in the list of facility emergency coordinators or equipment in the contingency plan constitutes a minor modification to the facility's Ohio hazardous waste permit to which the contingency plan is a condition.

Effective: 10/31/2015
Five Year Review (FYR) Dates: 07/01/2015 and 07/01/2020
Promulgated Under: 119.03
Statutory Authority: 3734.12
Rule Amplifies: 3734.12
Prior Effective Dates: 04/15/1981, 01/07/1983