3745-91-05 Requirements for data sheet.

The data sheet shall be on a form provided by the director and shall include information such as the title of the project, project location, identification of the ultimate owner, identification of the designer, estimated construction cost, basis of design, and such other information as may be required. Additional information may be required depending upon the type and complexity of the project under review.

Five Year Review (FYR) Dates: 10/26/2015 and 10/26/2020
Promulgated Under: 119.03
Statutory Authority: 6109.04
Rule Amplifies: 6109.03, 6109.04, 6109.07
Prior Effective Dates: 11/26/80