4901:1-18-07 Reconnection of service.

(A) Upon payment or proof of payment of the delinquent amount as stated on the disconnection notice, or of an amount sufficient to cure the default on an extended payment plan or the percentage of income payment plan (PIPP), applicable reconnection charge, the utility company shall reconnect service that has been disconnected for nonpayment pursuant to the following provisions:

(1) For customers disconnected from service for ten business days or less, the utility company may assess a reconnection charge and shall reconnect service by the close of the following regular utility company working day. Pursuant to rule 4901:1-18-05 of the Administrative Code, the amount sufficient to cure the default for customers on extended payment plans shall include all amounts that would have been due and owing under the terms of the applicable extended payment plan, absent default, on the date that service is reconnected. Under paragraph (D)(2)(b) of rule 4901:1-18-12 of the Administrative Code, the amount sufficient to cure the default for PIPP customers includes all amounts that would have been due for any missed PIPP payments, but not more than the arrearage balance.

(2) For customers disconnected from service for more than ten business days, the utility company may treat the customers as new customers and connect service consistent with the timeframes in rules 4901:1-10-09 , 4901:1-13-05 and paragraph (C) of rule 4901:1-17-04 of the Administrative Code. In addition, the utility company may assess the customer a reconnection charge in accordance with approved tariffs. Pursuant to paragraph (D)(2)(b) of rule 4901:1-18-12 of the Administrative Code, PIPP customers shall be required to pay any missed PIPP payments but not more than the arrearage balance. PIPP customers shall not be required to pay a deposit pursuant to rule 4901:1-18-15 of the Administrative Code.

(B) If service is disconnected for nonpayment for no more than ten business days and the customer wishes to guarantee the reconnection of service the same day on which payment is rendered:

(1) The customer must provide proof of payment, as required in paragraph (A)(1) of this rule to the utility company no later than twelve-thirty p.m.

(2) If the customer requests that reconnection occur after normal business hours, and such service is offered by the utility company, the utility company may require the customer to pay or agree to pay the utility company's approved tariff charges for after-hours reconnection. The utility company may collect this fee prior to reconnection or with the customer's next monthly billing.

(C) The utility company shall not assess a reconnection charge unless the utility company has actually disconnected the service. The utility company may, however, assess a collection charge if the collection charge is part of the utility company's approved tariff. A collection charge shall not be assessed more than once per billing cycle.

(D) If the utility company accepts a guarantor in order to reestablish service, it shall follow all of the requirements of paragraph (A)(5) of rule 4901:1-17-03 of the Administrative Code.

Replaces: 4901:1-18-06

Click to view Appendix

Click to view Appendix

Effective: 11/01/2010
R.C. 119.032 review dates: 11/30/2013
Promulgated Under: 111.15
Statutory Authority: 4905.04
Rule Amplifies: 4905.06 , 4905.22 , 4905.30 , 4933.12 , 4933.121 , 4933.122
Prior Effective Dates: 3/22/80, 10/6/82, 12/1/83, 9/1/04