4901:1-20-15 Final order.

So long as the commission has not found a proposed transition plan to be substantially inadequate and required refiling (in whole or in part), the commission shall, no later than two hundred seventy-five days after the date an electric utility files a transition plan (as well as supporting direct expert testimony) pursuant to section 4928.31 of the Revised Code, or October 31, 2000, whichever is earlier, issue a final order approving the transition plan as filed or an order modifying and approving that plan. If the commission does not issue a final order approving a transition plan or such final order is enjoined in whole or in part pending an appeal, the commission shall issue an interim order prescribing the transition plan to be in effect on an interim basis, consistent with section 4928.33 of the Revised Code.

R.C. 119.032 review dates: 08/02/2004 and 11/30/2008

Promulgated Under: 111.15

Statutory Authority: 4928.06

Rule Amplifies: 4928.32(C) , 4928.33

Prior Effective Dates: 3/10/00