Chapter 4901:1-22 Interconnection Services

4901:1-22-01 Definitions.

As used in this chapter:

(A) "Applicant" means the person requesting interconnection service and may be any of the following:

(1) A customer generator as defined by division (A)(29) of section 4928.01 of the Revised Code.

(2) A self-generator as defined by division (A)(32) of section 4928.01 of the Revised Code.

(3) The owner or operator of distributed generation as defined in paragraph (H) of this rule.

(B) "Application" means a request to an electric distribution utility (EDU) using the format set forth on the web site of the public utilities commission of Ohio for interconnection of distributed generation to the electric distribution system owned by the EDU.

(C) "Area network" means a type of electric distribution system served by multiple transformers interconnected in an electrical network circuit, which is generally used in large metropolitan areas that are densely populated, in order to provide highly reliable service. Area network has the same meaning as the term "distribution secondary grid network" found in institute of electrical and electronics engineers (IEEE) standard 1547 sub clause 4.1.4.

(D) "Backup electricity supply" means replacement electric power supplied to an applicant by the EDU at a tariff rate or alternatively, as a market-based option or by a competitive retail electric service provider of the applicant's choice at a rate to be determined between the provider and the applicant.

(E) "Commission" means the public utilities commission of Ohio.

(F) "Competitive retail electric service" means a component of retail electric service that is competitive as provided under division (B) of section 4928.01 of the Revised Code.

(G) "Cost recovery" means collection, upon approval by the commission pursuant to its authority under section 4909.15 of the Revised Code, of such documented EDU interconnection costs that are incurred at reasonable levels for prudent purposes and that are over and above the review processing fees set forth in rules 4901:1-22-06 to 4901:1-22-08 of the Administrative Code.

(H) Distributed generation" is a general term for all or part of a system of a distributed electrical generator or a static inverter either by itself or in the aggregate of twenty megawatts or less in size together with all protective, safety, and associated equipment installed at a point of common coupling on the EDU's distribution system in close proximity to the customer load.

(I) "Electric distribution utility" (EDU) means an investor-owned electric utility that owns and operates a distribution wires system and supplies at least retail electric distribution service.

(J) "Equipment package" means distributed generation facility assembled to include not only a generator or electric source but related peripheral devices that facilitate operation of the distributed generation.

(K) "Expedited procedure" means a review process for certified distributed generation that passes a certain prespecified review procedure, has a capacity rating of two megawatts or less, and does not qualify for simplified procedures.

(L) "Interconnection" means the physical connection of the applicant's facilities to the EDU's system for the purpose of electrical power transfers.

(M) "Interconnection point" means the point at which the applicant's distributed generation facility physically connects to the EDU's system.

(N) "Interconnection service" means the services provided by an EDU or transmission provider for the applicant's distributed generation facility.

(O) "Minor modification" to an interconnection application means a change in the technical characteristics that improves the reliability, safety and compatibility of the interconnection with the electric distribution system while not materially increasing the size or cost of the intended distributed generation facility installation.

(P) "Parallel operation with the EDU's system" means all electrical connections between the applicant's distributed generation facility and the EDU's system that are capable of operating in conjunction with each other.

(Q) "Point of common coupling" means the point which the distributed generation facility is connected to the EDU's system.

(R) "Reliability" means the degree of performance of the elements of the electric system that results in electricity being delivered to and from an applicant in the amount desired while avoiding adverse effects on the adequacy and security of the electric supply, defined respectively as:

(1) The ability of the electric system to supply the aggregate electrical demand and energy requirements at all times, taking into account scheduled and unscheduled outages of system elements.

(2) The ability of the electric system to withstand sudden disturbances such as electric short circuits or unanticipated loss of system elements.

(S) "Retail electric service provider" means any entity in this state that provides retail electric service as defined by division (A)(27) of section 4928.01 of the Revised Code.

(T) "Sale for resale" means a sale of energy to an energy supplier, electric utility or a public authority for resale purposes.

(U) "Scoping meeting" means a meeting between representatives of the applicant and the EDU conducted for but not limited to the following purposes:

(1) To discuss alternative interconnection options.

(2) To exchange information including any electric distribution system data and earlier study evaluations that would be expected to impact such interconnection options.

(3) To analyze such information.

(4) To determine the potential points of common coupling.

(V) "Simplified procedures" means a review process for interconnection of distributed generation fifty kilowatts or less in size on a radial or spot network system under certain conditions.

(W) "Standard procedure" means a review process for interconnection of any generating facility(s) that has a power rating of twenty megawatts or less, not qualifying for either simplified or expedited interconnection review processes.

(X) "Spot network," as defined by IEEE standard 1547 sub clause 4.1.4, means a type of electric distribution system that uses two or more inter-tied transformers to supply an electrical network circuit and is generally used to supply power to a single customer or a small group of customers.

Effective: 06/29/2009
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00, 10/22/07

4901:1-22-02 Scope and application.

(A) The rules in this chapter are intended to do all of the following:

(1) Make compliance within this chapter not unduly burdensome or expensive for any applicant in accordance with division (A) of section 4928.11 of the Revised Code.

(2) Establish uniform requirements for offering nondiscriminatory technology-neutral interconnection to customers who generate electricity, on the customer's side of the meter, to any electric distribution system that is owned and operated by a commission-regulated electric distribution utility (EDU) in Ohio, in a manner that protects public and worker safety and system reliability to the extent the commission's governing authority is not preempted by federal law.

(3) Apply in the entire territory where commission-approved tariffs apply to those situations where an applicant seeks to physically connect distributed generation to, and operate it in parallel with, the EDU's distribution system.

(4) Provide three review options for an applicant's request for interconnection with the EDU including simplified procedures, expedited procedures, and standard procedures.

(B) Each EDU in the state of Ohio shall file uniform interconnection service tariffs for commission review and approval pursuant to division (A) of section 4928.11 of the Revised Code, that includes the procedures and technical requirements set forth in this chapter for interconnection service on a first-come, first-served basis.

(C) The rules in this chapter shall not relieve any applicant from complying with all applicable federal, state, and local laws and ordinances.

Replaces: 4901:1-22-01

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00

4901:1-22-03 Industry standards.

The safety and performance standards established by the institute of electrical and electronics engineers, the underwriters laboratory, and the National Electric Code, as included in this chapter by reference, and as required consistent with division (B)(4) of section 4928.67 of the Revised Code, shall be the versions adopted in final form and effective as of July 31, 2008.

Effective: 06/29/2009
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 10/22/07

4901:1-22-04 General provisions.

(A) Prohibitions

(1) In accordance with the electric distribution utility's (EDU) code of conduct adopted pursuant to section 4928.17 of the Revised Code, an EDU or its affiliates shall not use, without the customer's consent, such knowledge of proposed interconnection service to prepare competing proposals to the interconnection service that offer either discounted rates in return for not providing the interconnection service or competing generation.

(2) No EDU shall reject, penalize, or discourage the use or development of new technology for interconnection service in accordance with division (A) of section 4928.11 of the Revised Code.

(B) Application processing

(1) EDUs shall process all applications for interconnection service and parallel operation with the EDU's system in a nondiscriminatory manner and in the order in which they are received.

(2) Where minor modifications to a pending application are required during the EDU's review of the application, such minor modifications shall not require a new or separate application to be filed by the applicant.

(3) The EDU shall automatically provide each applicant with a written notice of the EDU's receipt of an application within three business days after the application has been received. The notice of receipt shall include the following:

(a) A copy of the applicable review process.

(b) A target date for processing the application.

(4) If the EDU determines that the application is incomplete, the EDU personnel identified as being responsible for reviewing the application must provide the following:

(a) A written notice within ten business days after the application has been received indicating that the application is not complete.

(b) A checklist or description of the information needed to complete the application.

(c) A statement that processing the application cannot begin until the needed information is received.

(5) If an EDU determines that it cannot connect the applicant's facility within the time frames stated in this chapter, it will notify the applicant in writing of that fact within ten business days after the application has been received. The notification must include the following:

(a) The reason or reasons interconnection service could not be performed within the time frames stated in this rule.

(b) An alternative date for interconnection service.

(C) Compliance with national industry standards

An EDU shall file tariffs for uniform interconnection service with the commission that are consistent with the following:

(1) The institute of electric and electronics engineers 1547 standard, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(2) Underwriters laboratory 1741 standard for inverters, converters, and controllers for use in independent power systems, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(3) The appropriate criteria and interconnection parameters for the customer's technology, so as not to impose technical and economic barriers to new technology or the development, installation, and interconnection of an applicant's facilities, pursuant to division (A) of section 4928.11 of the Revised Code.

(D) Metering

Any metering installation, testing, or recalibration performed by the EDU at the request of the applicant for installation of the applicant's distributed generation facility shall be provided consistent with the electric service and safety standards pursuant to Chapter 4928. of the Revised Code, and rule 4901:1-10-05 and , as applicable, paragraph (C) of rule 4901:1-10-28 of the Administrative Code. Interconnection requested by the applicant for the purposes of net metering must follow the commission's net metering rules promulgated pursuant to division (A)(31) of section 4928.01 of the Revised Code. Any exception to the net metering rules shall be implemented in accordance with any special metering or communication infrastructure ordered by the commission.

(E) Disposal of excess energy produced by the applicant's distributed generation

(1) An applicant proposing to install a self-generator as defined in division (A)(32) of section 4928.01 of the Revised Code for the purposes of selling excess electricity to retail electric service providers as a competitive service to the extent not preempted by federal law must first seek certification of managerial, technical and financial capability consistent with section 4928.08 of the Revised Code.

(2) An applicant requesting interconnection for the purpose of selling energy to any party as a sale for resale or as a wholesale transaction may be subject to applicable rules for regional interstate sales at wholesale prices in markets operated by independent transmission system operators or regional transmission operators under the jurisdiction of the federal energy regulatory commission.

(F) Construction or system upgrades of the EDU's system

(1) Where construction or system upgrades of the EDU's system are required by the applicant's installation of a distributed generation facility, the EDU shall provide the applicant with an estimate of the timetable and the applicant's cost for the construction or system upgrades, consistent with the provisions of this chapter.

(2) If the applicant desires to proceed with the construction or system upgrades, the applicant and EDU shall enter into a contract for the completion of the construction or system upgrades.

(3) Interconnection service shall take place no later than two weeks following the completion of such construction or system upgrades.

Effective: 06/29/2009
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00, 10/22/07

4901:1-22-05 Application requirements for interconnection.

(A) Application forms

(1) Each applicant for interconnection to an electric distribution utility (EDU) system shall complete either of the following:

(a) A "short form" application for interconnection of generating equipment fifty kilowatts or less.

(b) A standard application for interconnection of generation equipment that does not qualify for a "short form" application.

(2) The application form shall follow the format and content set forth on the commission's website, and must be submitted to the EDU from which the applicant receives retail electric distribution service. Application forms will be available from the applicant's local EDU. The applicant's completed application form should not be sent to the commission for the purposes of review and approval.

(3) The applicant also is advised to refer to the "applicant's checklist" found on the commission website to determine whether to complete the "short form" or the standard form to request interconnection service.

(B) Certified equipment

(1) Each applicant shall provide the EDU a description of the applicant's distributed generation equipment package that is consistent with the following:

(a) An applicant's equipment package shall be considered certified for interconnected operation if it has been:

(i) Submitted by a manufacturer to a nationally recognized testing laboratory for certification.

(ii) Type-tested consistent with the institute of electrical and electronics engineers 1547.1 standard, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(iii) Listed by a nationally recognized testing and certification laboratory for continuous interactive operation with a utility grid in compliance with the applicable codes and standards listed in rule 4901:1-22-03 of the Administrative Code.

(b) Certified equipment does not include equipment provided by the EDU.

(C) Equipment packages

(1) An applicant's equipment package shall include the following:

(a) All interface components including switchgear, inverters, or other interface devices.

(b) An integrated generator or electric source.

(c) Access for the EDU for commissioning purposes.

(d) A schedule for periodic compliance testing.

(2) If the applicant's equipment package includes only the interface components (switchgear, inverters, or other interface devices), then the applicant must show in writing that the generator or electric source to be used with the equipment package meets the following criteria:

(a) Compatibility with the equipment package.

(b) Consistency with the testing and listing specified for the package.

(D) Disconnect switch

A disconnect switch provided, installed by, and paid for by the applicant, whether or not it is an integrated feature of the equipment package or a compatible external device, must meet the following criteria:

(1) The applicant's disconnect switch must be capable of isolating the distributed generation facility for the purposes of safety during EDU system maintenance and during emergency conditions.

(2) If the applicant's disconnect switch is external to the equipment package, it must be accessible to and lockable by the EDU personnel at either the primary voltage level, which may include load-break cutouts, switches and elbows, or the secondary voltage level, which may include a secondary breaker or switch.

(3) The applicant's disconnect switch must be clearly labeled as a distributed generation facility disconnect switch.

(E) Solar equipment

(1) In the case of solar equipment, the photovoltaic power source shall be clearly labeled in accordance with the requirements of the National Electric Code article 690, effective as set forth in rule 4901:1-22-03 of the Administrative Code, to identify the following:

(a) Operating current (a system maximum-power current).

(b) Operating voltage (system maximum-power voltage).

(c) Maximum system voltage.

(d) Short-circuit current.

(2) In the case of solar units with internal switching devices, a customer lock box containing a key to the applicant's premises where the solar unit is installed should be accessible to EDU personnel.

(F) The EDU's review processing fees

(1) Each applicant shall pay the EDU's interconnection fees in accordance with the EDU's tariff for the EDU review and processing of an application, established at levels consistent with the distributed generation size and technology as well as the location on the electric distribution system of the interconnection.

(2) The EDU's review processing fee levels will apply in accordance with the EDU's tariff to all interconnections, including those for the purposes of net metering, combined heat and power or waste heat from industrial processes, as well as any customer-generator used for energy efficiency or the promotion and utilization of renewable or clean secondary fuels.

(3) Exception to the EDU's fee schedule may be determined by the EDU if the EDU invokes a fee-free feature on a nondiscriminatory basis.

Replaces: part of 4901:1-22-04

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00

4901:1-22-06 Simplified procedures and fees for application processing.

(A) Level 1 simplified review procedure

(1) The electric distribution utility (EDU) shall review an applicant's completed interconnection service application that meets the criteria set forth in paragraph (A)(2) of this rule within four weeks of receiving the completed application.

(2) In order for the application to be approved by the EDU under the level 1 simplified review procedure, the applicant's generating facility must be an inverter-based system with a maximum nameplate capacity of ten kilowatts or less that uses renewable energy as fuel and the results of interconnecting the applicant's generating facility to the EDU's distribution system must comply with the following parameters:

(a) The applicant's proposed distributed generation facility's point of common coupling is not on a transmission line.

(b) The aggregated generation on the circuit, including the proposed distributed generation facility, may not exceed fifteen per cent of the peak load on the smallest part of the primary distribution system that could remain connected after operation of sectionalizing devices.

(c) The proposed distributed generation facility, in aggregation with other generation on the distribution circuit, shall not contribute more than ten per cent to the distribution circuit's maximum fault current at the point on the high voltage (primary) level nearest the proposed point of common coupling.

(d) The proposed distributed generation facility in aggregation with other generation located on the load side of a spot network shall not exceed five per cent of the spot network's maximum load when aggregated with other inverter-based generation.

(e) Direct current injection shall be maintained at or below five-tenths of a per cent of full rated inverter output current into the point of common coupling.

(f) When a proposed distributed generation facility is single phase and is to be interconnected on a center tap neutral of a two hundred forty volt service, its addition shall not create an imbalance between the two sides of the two hundred forty volt service of more than twenty per cent of the nameplate rating of the service transformer.

(g) The proposed distributed generation facility installation is certified to pass an applicable non-islanding test, or uses reverse power relays or other means to meet the unintentional islanding requirements of the institute of electrical and electronics engineers (IEEE) 1547 standard, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(h) The proposed distributed generation facility installation complies with the IEEE 1547 standard and Underwriters Laboratory 1741 standard, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(3) Having complied with the parameters set forth in paragraph (A)(2) of this rule, the applicant's proposed distributed generation facility installation requires no further study by the EDU for the purpose of interconnection to the EDU's distribution system.

(4) The EDU's tariff for a level 1 fee will be based on actual costs per one-tenth of an hour of time spent on the simplified review, and not on a flat rate.

(5) Construction of facilities by the EDU on its own system is not required to accommodate the distributed generation facility.

(6) Within five days after completion of the level 1 simplified procedure leading to the EDU's approval for interconnection of the applicant's distributed generation facility, the EDU shall provide the applicant with a standard interconnection agreement. The standard interconnection agreement shall be consistent with the uniform requirements for an interconnection agreement enumerated in rule 4901:1-22-10 of the Administrtive Code and include a timetable for the physical interconnection of the applicant's proposed distributed generation facility to the EDU's system.

(B) Level 1.1 simplified review procedure

(1) The EDU shall review an applicant's completed interconnection service application that meets the criteria set forth in paragraph (B)(2) of this rule within four weeks of receiving a completed application, except that the EDU shall have an additional twenty business days to conduct an area network impact study to determine potential adverse impacts of interconnecting to its area network.

(2) In order for the application to be approved by the EDU under the level 1.1 simplified review procedure, the generating unit must be an inverter-based system with a maximum nameplate capacity of ten kilowatts or less and the results of interconnecting the applicant's generating facility to the EDU's distribution system must comply with the following parameters:

(a) The proposed distributed generation facility's point of common coupling is not on a transmission line.

(b) The interconnection is to be located on the load side of an area network.

(c) The aggregated other generation on the area network does not exceed five per cent of an area network's maximum load.

(d) The proposed distributed generation facility installation is certified to pass an applicable non-islanding test, or uses reverse power relays or other means to meet IEEE 1547 standard unintentional islanding requirements, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(3) The EDU's tariff for a level 1.1 fee will be based on actual costs per one-tenth of an hour of time spent on the simplified review, and not on a flat rate.

(4) Any area network impact study shall be conducted at the EDU's own expense.

(5) Construction of facilities by the EDU on its own system is not required to accommodate the distributed generation facility.

(6) Within five days after completion of the level 1.1 simplified procedure leading to the EDU's approval for interconnection of the applicant's distributed generation facility, the EDU shall provide the applicant with a standard interconnection agreement. The standard interconnection agreement shall be consistent with the uniform requirements for an interconnection agreement enumerated in rule 4901:1-22-10 of the Administrative Code and include a timetable for the physical interconnection of the applicant's proposed distributed generation facility to the EDU's system.

(7) When an area network impact study identifies potential adverse system impacts, the EDU may determine that it is inappropriate for the distributed generation facility to interconnect to the area network and the application filed for level 1.1 review shall be denied.

(a) When the EDU denies a level 1.1 application, it shall provide the applicant with a copy of the area network impact study and a written justification for denying the interconnection request.

(b) Upon denial of the level 1.1 interconnection request, the applicant may elect to submit a new application for consideration under level 2 or level 3 procedures, in which case the queue position assigned to the level 1.1 application shall be retained.

(C) Level 1.2 simplified review procedure

(1) The EDU shall review a completed interconnection service application that meets the criteria set forth in paragraph (C)(2) of this rule within four weeks of receiving a completed application, except that the EDU shall have an additional twenty-five days to conduct an area network impact study to determine any potential adverse impacts of interconnecting to its area network.

(2) In order for the application to be approved by the EDU under the level 1.2 simplified review procedure, the generating unit must be a certified inverter-based system with a maximum nameplate capacity of equal to fifty kilowatts or less and the results of interconnecting the applicant's generating facility to the EDU's distribution system must comply with the following parameters:

(a) The interconnection is to be to an area network distribution system.

(b) The proposed distributed generation facility installation is certified to pass an applicable non-islanding test, or uses reverse power relays or other means to meet IEEE 1547 standard unintentional islanding requirements, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(c) The proposed level 1.2 distributed generation facility meeting level 1.1 parameters in paragraphs (B)(2)(a) to (B)(2)(d) of this rule shall be presumed to be appropriate for interconnecting to an area network

(3) The EDU's tariff for a level 1.2 fee will be based on actual costs per one-tenth of an hour of time spent on the simplified review, and not on a flat rate.

(4) Any area network impact study shall be conducted at the EDU's own expense.

(5) Within five days after completion of the level 1.2 simplified procedure leading to the EDU's approval for interconnection of the applicant's distributed generation facility, the EDU shall provide the applicant with a standard interconnection agreement. The standard interconnection agreement shall be consistent with the uniform requirements for an interconnection agreement enumerated in rule 4901:1-22-10 of the Administrative Code and include a timetable for the physical interconnection of the applicant's proposed distributed generation facility to the EDU's system.

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11

4901:1-22-07 Expedited procedures.

Level 2 expedited review process

(A) The electric distribution utility (EDU) shall review an applicant's completed interconnection service application that meets the criteria set forth in paragraph (B) of this rule on an expedited basis.

(B) In order for the application to be approved by the EDU under the level 2 expedited review procedure, the applicant's proposed certified inverter-based or synchronous distributed generation facility in aggregation with all other generators on the EDU's circuit must be two megawatts or less and the results of interconnecting the applicant's generating facility to the EDU's distribution system must comply with the following parameters:

(1) The proposed distributed generation facility's point of interconnection shall not be on a transmission line

(2) The interconnection is to a radial distribution circuit.

(3) The proposed distributed generation facility complies with institute of electrical and electronics engineers (IEEE) 1547 standard and underwriters uaboratory 1741 standard, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(4) The proposed distributed generation facility, in aggregation with other generation interconnected to the distribution side of a substation transformer feeding the circuit where the distributed generation facility proposes to interconnect, shall not exceed two megawatts in an area where there are known or posted transient stability limitations to generating units located in the general electrical vicinity (for example, three or four distribution busses from the point of interconnection).

(5) The proposed distributed generation's capacity in aggregation with other generation on the circuit shall not exceed fifteen per cent of the total circuit peak load as most recently measured at the substation; nor will it exceed fifteen per cent of a distribution circuit line section annual peak load.

(6) The proposed distributed generation facility, in aggregation with other generation on the distribution circuit, shall not contribute more than ten per cent to the distribution circuit's maximum fault current at the point on the primary voltage distribution line nearest the point of common coupling.

(7) The proposed distributed generation facility, in aggregation with other generation on the distribution circuit, may not cause any distribution protective devices and equipment (including substation breakers, fuse cutouts, and line reclosers), or other customer equipment on the electric distribution system to be exposed to fault currents exceeding eighty-five per cent of the short circuit interrupting capability.

(8) The applicant shall not request interconnection on a circuit that already exceeds eighty-five per cent of the short circuit interrupting capability.

(9) When a proposed distributed generation facility is single phase and is to be interconnected on a center tap neutral of a two hundred forty volt service, its addition shall not create an imbalance between the two sides of the two hundred forty volt service of more than twenty per cent of the nameplate rating of the service transformer.

(10) The proposed distributed generation facility installation is certified to pass an applicable non-islanding test, or uses reverse power relays or other means to meet IEEE 1547 standard unintentional islanding requirements, effective as set forth in rule 4901:1-22-03 of the Administrative Code.

(11) On a three-phase, three-wire primary electric distribution line, a three- or single-phase generator shall be connected phase-to-phase.

(12) When the applicant's facility is to be connected to three-phase, four-wire primary EDU distribution lines, a three- or single-phase generator will be connected line-to-neutral and will be effectively grounded.

(13) A review of the type of electrical service provided to the applicant, including line configuration and the transformer connection, will be conducted to limit the potential for creating over voltages on the EDU's electric distribution system due to a loss of ground during the operating time of any anti-islanding function.

(14) When the proposed distributed generation facility is to be interconnected on single-phase shared secondary line, the aggregate generation capacity on the shared secondary line, including the proposed distributed generation facility, will not exceed ten kilowatts.

(15) Construction of facilities by the EDU on its own system is not required to accommodate the distributed generation facility.

(C) The EDU's tariff for level 2 expedited review processing fees will include the following:.

(1) An application fee of up to fifty dollars, plus one dollar per kilowatt of the applicants' system nameplate capacity rating.

(2) The cost of engineering work done as part of any impact or facilities study, billed at actual costs incurred.

(3) The actual cost of any minor modification of the electric distribution utility's system that would otherwise not be done but for the applicant's interconnection request

(D) When an EDU determines that the application passes the level 2 review process, or fails one or more of the level 2 criteria set forth in paragraph (B) of this rule but the EDU determines that the distributed generation facility can be interconnected safely and reliably, the EDU shall provide the applicant with a standard distributed generation interconnection agreement within five business days after such determination. The standard interconnection agreement shall be consistent with the uniform requirements for an interconnection agreement enumerated in rule 4901:1-22-10 of the Administrative Code and include a timetable for the physical interconnection of the applicant's proposed distributed generation facility to the EDU's system.

(E) When additional review by the EDU may be appropriate for an application failing to meet one or more of the level 2 criteria, the EDU shall offer to do the following for the applicant:

(1) Perform additional review to determine whether minor modifications to the electric distribution system would enable the interconnection to be made consistent with safety, reliability and power quality criteria.

(2) Provide the applicant with a nonbinding, good faith estimate of the EDU's costs of additional review and minor modifications.

(3) Notify the applicant that the additional review or modifications will be undertaken only after the applicant consents in writing to pay for the review and modifications.

(F) Within five days after completion of the level 2 expedited procedure leading to the EDU's approval for interconnection of the applicant's proposed distributed generation facility installation and collection by the EDU of the applicant's payment pursuant to paragraph (E)(3) of this rule, the EDU shall provide the applicant with a standard interconnection agreement. The standard interconnection agreement shall be consistent with the uniform requirements for an interconnection agreement enumerated in rule 4901:1-22-10 of the Administrative Code and include a mutually agreed upon timetable for the physical interconnection of the applicant's proposed distributed generation facility to the EDU's system.

Replaces: part of 4901:1-22-04

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00

4901:1-22-08 Standard procedure.

Level 3 standard review procedure

(A) Level 3 standard review procedure shall use the determinations made in the scoping meeting and the interconnection studies defined in rule 4901:1-22-09 of the Administrative Code for technical analysis of the applicant's proposed distributed generation facility installation.

(B) Level 3 is applicable for systems that do not qualify for either level 1 or level 2 review procedures. In order for the application to be approved under the level 3 standard review procedure, the applicant's inverter-based or synchronous distributed generation facility, either individually or in the aggregate, must have a nameplate capacity of twenty megawatts or less, and the results of interconnecting the applicant's generating facility to a radial distribution circuit on the electric distribution utility's (EDU) distribution system must comply with any of the following applicable parameters:

(1) The distributed generation facility is less than two megawatts and is not certified or the distributed generation facility is less than two megawatts and non-inverter based.

(2) Known or posted transient stability limits to generating units located in the general electrical vicinity of the proposed point of common coupling require the proposed application to be subject to a level 3 standard review process.

(3) The application's failure to meet any criteria under level 2 for the expedited process requires the EDU to use the level 3 interconnection procedures.

(4) The application was considered but not approved under a level 2 review and the applicant is submitting a new interconnection request for consideration under a level 3 review procedure. The queue position assigned to the level 2 interconnection application in accordance with paragraph (C) of rule 4901:1-22-09 of the Administrative Code shall be retained.

(C) The EDU's tariff for level 3 standard review fees will include the following:

(1) An application fee of up to one hundred dollars, plus two dollars per kilowatt of the system's nameplate capacity.

(2) In addition to the level 3 standard review application fee, any or all of the following fees may be assessed by the EDU:

(a) The cost of engineering work done as part of any feasibility, system impact or facilities study, billed at actual cost.

(b) The actual cost of any modifications of the EDU's system that would otherwise not be done but for the applicant's interconnection request.

(D) Within five days after completion of the level 3 standard procedure including any applicable feasibility, system impact or facilities studies leading to the EDU's approval for interconnection of the applicant's proposed distributed generation facility installation and collection by the EDU of all the actual costs for the studies as billed to the applicant, the EDU shall provide the applicant with a standard interconnection agreement. The standard interconnection agreement shall be consistent with the uniform requirements for an interconnection agreement enumerated in rule 4901:1-22-10 of the Administrative Code, and a mutually agreed upon timetable for the physical interconnection of the applicant's proposed distributed generation facility to the EDU's system.

Replaces: part of 4901:1-22-04

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00

4901:1-22-09 Scoping meeting and interconnection studies.

(A) The electric distribution utility (EDU)_will designate an employee or office from which information on the requirements for EDU's application review process can be obtained through an informal request by the applicant during a scoping meeting that includes discussion of the following:

(1) The applicant's proposed interconnection of a distributed generation facility at a specific location on the EDU's distribution system.

(2) Qualifications under EDU's level 1, level 2 or level 3 review procedures.

(3) Existing EDU studies relevant to the interconnection request.

(4) Reasonable requests from the applicant for EDU information including relevant system studies as well as other material useful to an understanding of an interconnection at a particular point on the system to the extent such information does not violate confidentiality provisions of prior agreements or critical infrastructure requirements.

(B) Scheduling of a scoping meeting will be established within ten business days after the scoping meeting has been requested by the applicant or as agreed to by the parties.

(C) Queuing

(1) When an interconnection request is complete, the EDU shall assign the application a queue position to establish the order in which the interconnection request will be reviewed in relation to other interconnection requests on the same or nearby sections of the EDU's distribution system.

(2) The queue position of an interconnection request shall be used to determine the cost responsibility necessary for the construction of any facilities to accommodate the interconnection in relation to other interconnection requests on the same or nearby sections of the EDU's distribution system.

(3) The EDU shall notify the applicant at the scoping meeting about other higher-queued applicants.

(D) Interconnection study requirements

(1) A specific interconnection study may be required by the EDU prior to interconnection service that will include the following:

(a) Each type of study required will include an EDU interconnection tariff fee schedule approved by the commission.

(b) Each type of study will be the subject of a written agreement between the applicant and the EDU that includes the following:

(i) A target date for completion of any required feasibility study, system impact study, and facilities study.

(ii) A provision to share the results of the study by the EDU with the applicant.

(c) The written agreement discussed in paragraph (D)(1)(b) of this rule may include an alternative provision that allows the required studies related to the interconnection of the generating facility(s) to be conducted by a qualified third party with the consent of the EDU.

(d) A written statement provided to the applicant by the EDU prior to the study that includes the following:

(i) A clear explanation of all charges.

(ii) A good faith estimate of the number of hours that will be needed to complete the study.

(iii) An estimate of the total interconnection study fee.

(2) By mutual agreement of the parties, a feasibility study, a system impact study, or a facilities study under level 3 procedures may be waived by the EDU.

(3) When the EDU determines, as a result of the studies conducted under a level 3 review, that it is appropriate to interconnect the distributed generation facility, the EDU shall provide the applicant with a standard distributed generation interconnection agreement. The standard interconnection agreement shall incorporate the uniform requirements for an interconnection agreement enumerated in rule 4901:1-22-10 of the Administrative Code, and a mutually agreed upon timetable for the physical interconnection of the applicant's proposed distributed generation facility to the EDU's system.

(4) If the interconnection request is denied, the EDU shall provide a written explanation within five days from the denial. The EDU must allow the applicant thirty days to cure the reasons for denial while the applicant's position in the queue is maintained.

(E) The feasibility study

(1) No later than five business days after the scoping meeting, the EDU shall provide the applicant with a feasibility study agreement in accordance with the EDU's tariff to determine the feasibility of interconnecting the applicant's proposed distributed generation facility at a particular point on the EDU's system. The study shall include both of the following:

(a) An outline of the scope of the study.

(b) A non-binding good faith estimate of the cost to perform the study.

(2) A feasibility study shall include the following analyses for the purpose of identifying a potential adverse system impact to the EDU's system that would result from the interconnection:

(a) Initial identification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection.

(b) Initial identification of any thermal overload or voltage limit violations resulting from the interconnection.

(c) Initial review of grounding requirements and system protection.

(d) A description and nonbinding estimated cost of facilities required to interconnect the distributed generation facility to the EDU's system in a safe and reliable manner.

(3) When an applicant requests that the feasibility study evaluate multiple potential points of interconnection, additional evaluations may be required.

(4) The actual cost of the EDU's additional evaluations shall be paid by the applicant.

(F) The system impact study

(1) No later than five business days after the completion of or a waiver of the feasibility study, the EDU shall provide a distribution system impact study agreement to the applicant, using a form of system impact study agreement in accordance with the EDU's tariff that includes an outline of the scope of the study and a nonbinding good faith estimate of the cost to perform the study.

(2) If the feasibility study concludes there is no adverse system impact, or the study identifies an adverse system impact but the EDU is able to identify a remedy, no system impact study is required.

(3) A system impact study shall evaluate the impact of the proposed interconnection on the safety and reliability of the EDU's system. The study shall:

(a) Identify and detail the system impacts that result when a distributed generation facility is interconnected without project or system modifications.

(b) Consider the adverse system impacts identified in the feasibility study, or potential impacts including those identified in the scoping meeting.

(c) Consider all generating facilities that, on the date the system impact study is commenced, are directly interconnected with the EDU's system.

(d) Consider pending higher queue position of facilities requesting interconnection to the system, or consider pending higher queue position of facilities requesting interconnection having a signed interconnection agreement.

(4) A system impact study performed by the EDU shall consider the following criteria:

(a) A load flow study.

(b) A short circuit analysis.

(c) A stability analysis.

(d) Voltage drop and flicker studies.

(e) Protection and set point coordination studies.

(f) Grounding reviews.

(5) The EDU shall state the underlying assumptions of the study and show the results of the analyses to the applicant, including the following:

(a) Any potential impediments to providing the requested interconnection service.

(b) Any required distribution system upgrades and provide a nonbinding good faith estimate of cost and time to construct the system upgrades.

(G) The facilities study

(1) Within five business days of completion of the system impact study, a report will be transmitted by the EDU to the applicant with a facilities study agreement in accordance with the EDU's interconnection tariff.

(2) When the parties agree at the scoping meeting that no system impact study is required, the EDU shall provide to the applicant, no later than five business days after the scoping meeting, a facilities study agreement in accordance with the EDU's interconnection tariff that enables the EDU to determine the interconnection facilities needed to interconnect the applicant's proposed distributed generation facility at a particular point on the EDU's system.

(3) The facilities study agreement shall include both of the following:

(a) An outline of the scope of the study.

(b) A nonbinding good faith estimate of the cost to perform the study to cover the cost of the equipment, engineering, procurement and construction work, including overheads, needed to implement the conclusions of the feasibility study and/or the system impact study to interconnect the distributed generation facility.

(4) The facilities study shall identify all of the following:

(a) The electrical switching configuration of the equipment, including transformer, switchgear, meters, and other station equipment.

(b) The nature and estimated cost of the EDU's interconnection facilities and distribution upgrades necessary to accomplish the interconnection.

(c) An estimate of the time required to complete the construction and installation of such facilities.

(5) The parties may agree to permit an applicant to separately arrange for a third party to design and construct the required interconnection facilities under the following conditions:

(a) The EDU may review the facilities to be designed and constructed by a third party under provisions included in the facilities study agreement for that purpose.

(b) The applicant and the third party separately arranging for design and construction agree to comply with security and confidentiality requirements.

(c) The EDU shall provide the applicant with all relevant information and required specifications available to permit the applicant to obtain an independent design and cost estimate for the facilities, which must be built in accordance with the specifications.

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11

4901:1-22-10 Uniform requirements for interconnection agreements.

(A) The electric distribution utility (EDU) shall provide the applicant with a standard interconnection agreement for distributed generation within five business days. If applicable, the applicant must pay for the interconnection facilities and distribution upgrades identified in the facilities study.

(B) The applicant shall have thirty business days or another mutually agreeable time frame after the standard interconnection agreement is received to sign and return the interconnection agreement to the EDU.

(C) When the applicant does not sign the agreement within thirty business days, the interconnection request will be deemed withdrawn unless the applicant requests an extension of the deadline in writing. The request for extension shall not be denied by the EDU, unless conditions on the EDU system have changed.

(D) Milestones for construction

(1) When construction is required, the interconnection of the distributed generation will proceed according to any milestones agreed to by the parties in the standard interconnection agreement.

(2) The interconnection agreement may not become effective until the milestones agreed to in the standard interconnection agreement are satisfied, including the following:

(a) The distributed generation is approved by electric code officials with jurisdiction over the interconnection.

(b) The applicant provides a certificate of completion to the EDU; or there is a successful completion of an on-site operational test within ten business days or at a mutually convenient time, unless waived. The operational test shall be observed by EDU personnel or a qualified third party with sufficient expertise to verify that the criteria for testing have been met.

(E) Insurance

(1) Any EDU interconnection agreement with the applicant shall not require additional liability insurance beyond proof of insurance or any other suitable financial instrument sufficient to meet its construction, operating and liability responsibilities in accordance with the EDU's tariff with respect to this rule.

(2) At no time shall the EDU require the applicant to negotiate any policy or renewal of any policy covering any liability through a particular insurance agent, solicitor, or broker.

(F) Alternative dispute resolution

The EDU or the applicant who is a nonmercantile, nonresidential customer may seek resolution of any disputes which may arise out the EDU tariffs filed under these rules, in accordance with Chapter 4901:1-26 of the Administrative Code, for alternative dispute resolution procedures.

(G) Site testing

The applicant must provide the EDU a reasonable opportunity to witness the testing of installed switchgear, protection system, and generator as included in the applicant's installation test plan and maintenance schedule that has been reviewed and approved by the EDU.

(H) Periodic testing

(1) Any periodic tests of the interconnection equipment (including any relays, interrupting devices, control schemes, and batteries that involve protection of the EDU's system) as recommended by the applicant's equipment manufacturer or required by the institute of electrical and electronics engineers (IEEE) 1547 standards, effective as set forth in rule 4901:1-22-03 of the Administrative Code, shall be the responsibility of the applicant.

(2) Such periodic tests shall be included in the applicant's installation test plan and maintenance schedule that has been reviewed and approved by the EDU.

(3) The applicant shall make copies of the periodic test reports or inspection logs available to the EDU for review.

(4) Upon a written request, the EDU is to be informed of the next scheduled maintenance and be able to witness the maintenance program and any associated testing.

(I) Disconnection of the applicant's facility

Except as provided for in paragraph (J)(2) of this rule, when the EDU discovers the applicant's equipment is not in compliance with IEEE 1547 standards, effective as set forth in rule 4901:1-22-03 of the Administrative Code, and such noncompliance has the potential to adversely affect the safety and reliability of the electric system, the EDU may disconnect the applicant's facility according to the following procedures:

(1) The EDU shall provide a notice to the applicant with a description of the specific noncompliance condition.

(2) The disconnection can only occur after a reasonable time to cure the noncompliance condition has elapsed.

(J) Other disconnection of the unit

(1) The applicant retains the option to temporarily disconnect from the EDU's system at any time. Such temporary disconnection shall not be a termination of the interconnection agreement unless the applicant exercises its termination rights under the interconnection agreement.

(2) The EDU shall have the right to disconnect the applicant's unit(s) without notice in the event of an emergency or to eliminate conditions that constitute a potential hazard to the EDU personnel or the general public. The EDU shall notify the applicant of the emergency as soon as circumstances permit.

(K) Service interruption

During routine maintenance and repairs on the EDU's system consistent with Chapter 4901:1-23 of the Administrative Code, or other commission order, the EDU shall provide the applicant with a seven-day notice of service interruption.

(L) Effective term and termination rights of an interconnection agreement

(1) An interconnection agreement becomes effective when executed by both parties and shall continue in force until terminated under any of the following conditions:

(a) The applicant terminates the interconnection agreement at any time by giving the EDU sixty days prior notice.

(b) The EDU terminates the interconnection agreement upon failure of the applicant to generate energy from the applicant's facility in parallel with the EDU's system by the later of two years from the date of the executed interconnection agreement or twelve months after completion of the interconnection.

(c) Either party terminates by giving the other party at least sixty days prior written notice that the other party is in default of any of the material terms and conditions of the interconnection agreement, so long as the notice specifies the basis for the termination and there is reasonable opportunity to cure the default.

(2) All applicants' installations existing on or before the effective date of this rule are exempted from the changes instituted by this rule.

(3) Upon termination of an interconnection agreement, the applicant's facilities will be disconnected from the EDU's system.

(4) The termination of the interconnection agreement shall not relieve either party of its liabilities and obligations, owed or continuing at the time of the termination.

Replaces: 4901:1-22-03

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00

4901:1-22-11 Backup electricity supply.

Replacement electric power for the applicant shall be supplied in accordance with division (C) of section 4928.15 of the Revised Code, by either of the following:

(A) The electric distribution utility either at a tariff rate or at the market price as provided for in its tariff.

(B) By the applicant's competitive retail electric service provider at a rate to be determined by contract.

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11

4901:1-22-12 Complaints.

All formal complaints brought by applicants or interconnection service customers pursuant to section 4905.26 of the Revised Code, will be handled according to the procedural standards set forth in Chapters 4901-1 and 4901-9 of the Administrative Code. Each electric distribution utility must provide to the commission utilities department the name and telephone number of a contact person to assist the commission staff with the resolution of informal complaints regarding provisions in Chapter 4901:1-22 of the Administrative Code.

Effective: 10/22/2007
R.C. 119.032 review dates: 09/30/2012
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11

4901:1-22-13 Exceptions.

Except where rule requirements are mandated by federal or state law, the commission may waive any provision contained in this chapter for good cause upon its own motion or upon application by a company.

R.C. 119.032 review dates: 04/24/2014 and 04/24/2019
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 10/22/07