Rule 4901:1-36-04 | Limitations.

 

(A) The transmission cost recovery rider costs are reconcilable on an annual basis, with carrying charges to be applied to both over- and under-recovery of costs.

(B) The transmission cost recovery rider shall be avoidable by all customers who choose alternative generation suppliers and the electric utility no longer bears the responsibility of providing generation and transmission service to the customers.

(C) The transmission cost recovery rider shall include transmission and transmission-related costs and off-setting revenues, including ancillary and congestion-related costs and revenues, charged or credited to the utility by the entity with control of transmission facilities under section 4928.12 of the Revised Code to the extent such costs and revenues are not included in any other schedule or rider in the electric utility's tariff on file with the commission.

Last updated January 8, 2024 at 8:39 AM

Supplemental Information

Authorized By: R.C. 4928.06
Amplifies: R.C. 4928.05, 4928.143
Five Year Review Date: 7/15/2026