4901:1-43-02 Purpose and scope.

(A) This chapter authorizes a natural gas company to file an application with the commission for approval of an infrastructure development rider to recover prudently incurred infrastructure development costs of one or more economic development projects approved under section 4929.163 or 4929.164 of the Revised Code.

(B) The commission may, upon an application or a motion filed by a party, waive any requirement of this chapter, other than a requirement mandated by statute, for good cause shown.

Effective: 9/29/2016
Five Year Review (FYR) Dates: 09/19/2021
Promulgated Under: 111.15
Statutory Authority: 4929.163, 4929.164, 4929.10
Rule Amplifies: 4929.16 , 4929.161, 4929.162, 4929.163, 4929.164, 4929.165, 4929.166, 4929.167