4906-1-14 Site visits.

Persons proposing, owning or operating major utility facilities or wind farms should make all reasonable efforts to ensure that, upon prior notification, the board, its representatives, or staff may make visits to proposed or alternative sites or routes of a major utility facility or wind farm or a substantial addition in order to carry out board responsibilities pursuant to Chapter 4906. of the Revised Code.

Effective: 05/07/2009
R.C. 119.032 review dates: 11/30/2013
Promulgated Under: 111.15
Statutory Authority: 4906.03 , 4906.20
Rule Amplifies: 4906.03 , 4906.13 , 4906.20
Prior Effective Dates: 12/27/76, 6/10/89, 12/15/03, 1/25/09