Rule 4906-3-02 | Preapplication conference.

 

An applicant considering construction of a major utility facility or economically significant wind farm may request a preapplication conference with the board staff prior to submitting an application. The results of such conference(s) shall in no way constitute approval or disapproval of a particular site or route, and shall in no way predetermine the board's decision regarding subsequent certification or approval.

Last updated March 13, 2024 at 3:28 PM

Supplemental Information

Authorized By: 4906.03, 4906.20
Amplifies: 4906.03, 4906.04, 4906.06, 4906.10, 4906.13, 4906.20
Five Year Review Date: 11/25/2021
Prior Effective Dates: 12/27/1976, 6/10/1989, 8/28/1998, 12/15/2003, 1/25/2009, 5/7/2009