Rule 4906-3-04 | Combined standard and accelerated certificate applications.

 

(A) If a project that qualifies for accelerated review is an associated facility of a major utility facility that is subject to filing a standard certificate application with the board, the projects may be combined into one standard certificate application.

(B) Electric generation plants and associated electric transmission or gas pipeline projects that do not qualify for accelerated review shall be filed in separate standard certificate applications.