4906-5-01 Preapplication conference.

An applicant considering construction of a major utility facility or wind farm may request a preapplication conference with the board staff prior to submitting an application. The results of such conference(s) shall in no way constitute approval or disapproval of a particular site or route, and shall in no way predetermine the board's decision regarding subsequent certification or approval.

Effective: 05/07/2009
R.C. 119.032 review dates: 11/30/2013
Promulgated Under: 111.15
Statutory Authority: 4906.03 , 4906.20
Rule Amplifies: 4906.03 , 4906.13 , 4906.20
Prior Effective Dates: 12/27/76, 6/10/89, 8/28/98, 12/13/03, 1/25/09