Prior to including incentive/disincentive provisions in a contract, the director shall conduct an engineering analysis in order to determine realistic critical and non-critical time frames. The time frames, including critically identified work phase or phases, shall be clearly set out in the construction contract. The analysis should involve a review of industry past performance and a critical path method schedule.