5501:2-7-03 Determination of incentive/disincentive daily amount.

Prior to including incentive/disincentive provisions in a contract the director shall calculate on a per project basis a daily incentive/disincentive amount considering: construction engineering inspection costs, departmental traffic control costs and maintenance, detour and road user costs. The incentive daily rate may equal the disincentive rate.

R.C. 119.032 review dates: 07/12/2006 and 07/12/2011

Promulgated Under: 119.03

Statutory Authority: 5525.20

Rule Amplifies: 5525.20

Prior Effective Dates: 9/29/89