Rule 4906-4-05 | Electric grid interconnection.

 

(A) The applicant shall describe how the facility will be connected to the regional electric grid.

(B) The applicant shall provide information on interconnection of the facility to the regional electric power grid.

(1) The applicant shall provide information relating to their generation interconnection request, including interconnection queue name, number, date, and website.

(2) The applicant shall provide system studies on their generation interconnection request. The studies shall include, but are not limited to, the feasibility study and system impact study.

Last updated March 13, 2024 at 3:28 PM

Supplemental Information

Authorized By: 4906.03, 4906.20
Amplifies: 4906.03, 4906.04, 4906.06, 4906.10, 4906.13, 4906.20
Five Year Review Date: 11/25/2021