Skip to main content
Back To Top Top Back To Top
The Legislative Service Commission staff updates the Revised Code on an ongoing basis, as it completes its act review of enacted legislation. Updates may be slower during some times of the year, depending on the volume of enacted legislation.

Section 5705.44 | Contracts running beyond fiscal year - certificate not required on contracts payable from utility earnings.

 

When contracts or leases run beyond the termination of the fiscal year in which they are made, the fiscal officer of the taxing authority shall make a certification for the amount required to meet the obligation of such contract or lease maturing in such fiscal year. The amount of the obligation under such contract or lease remaining unfulfilled at the end of a fiscal year, and which will become payable during the next fiscal year, shall be included in the annual appropriation measure for the next year as a fixed charge.

The certificate required by section 5705.41 of the Revised Code as to money in the treasury shall not be required for contracts on which payments are to be made from the earnings of a publicly operated water works or public utility, but in the case of any such contract made without such certification, no payment shall be made on account thereof, and no claim or demand thereon shall be recoverable, except out of such earnings. That certificate also shall not be required if requiring the certificate makes it impossible for a county board of developmental disabilities to pay the nonfederal share of medicaid expenditures that the county board is required by sections 5126.059 and 5126.0510 of the Revised Code to pay.

Available Versions of this Section