Chapter 4901:5-3 | Filing of Long-Term Forecast Reports; Fees

 
 
 
Rule
Rule 4901:5-3-01 | Long-term forecast report due dates.
 

(A) All electric transmission owners or electric utilities required by section 4935.04 of the Revised Code to file a long-term forecast report must file annually on or before April fifteenth.

(B) All gas and natural gas distribution companies required by section 4935.04 of the Revised Code to file a long-term forecast report must file every three years on or before June first.

(C) Notwithstanding the requirements of paragraphs (A) and (B) of this rule, the commission may grant an extension of the filing deadline for good cause shown.

Last updated June 5, 2023 at 8:39 AM

Supplemental Information

Authorized By: R.C. 4935.04, 4901.13
Amplifies: R.C. 4935.04
Five Year Review Date: 5/25/2028
Prior Effective Dates: 1/15/1990, 3/24/1997, 9/18/2000
Rule 4901:5-3-02 | Fees.
 

(A) Fees for electric transmission owners or electric utilities shall be submitted annually to the commission on or before May first.

(B) Fees for gas and natural gas distribution companies shall be submitted every three years to the commission on or before September fifteenth.

(C) All fee payments shall be made in a manner as prescribed by the commission.

(D) The commission shall annually determine the fee each utility must pay, and shall notify each utility as to that amount at least thirty days prior to the date payment is due.

(E) Fees for electric transmission owners or electric utilities will be based on:

(1) For electric transmission owners, the fee shall be two and one-half mills per megawatt hour delivery based upon the energy deliveries for loads connected to the system inside Ohio for the most recent year for which actual data is reported on the most recently filed form FE-T1.

(2) For electric utilities, the fee shall be two and one-half mills per megawatt-hour delivery based upon the net energy for load for the most recent year for which actual data is reported on the most recently filed form FE-D1.

(F) Fees for gas and natural gas distribution companies will be based on two factors:

(1) In-state total number of meters in December of the preceding year, as reported to the commission on form SG-1.

(2) Total in-state sales for the most recent calendar year for which actual data are reported to the commission on the most recently filed form SG-1.

(G) Annual fees for gas and natural gas distribution companies shall be the sum of the following charges:

(1) One hundred mills per meter.

(2) Two hundred ninety-seven mills per million cubic feet.

Last updated June 5, 2023 at 8:39 AM

Supplemental Information

Authorized By: R.C. 4935.04, 4901.13
Amplifies: R.C. 4935.04
Five Year Review Date: 5/25/2028
Prior Effective Dates: 2/12/2012