Rule 1301:3-5-05.1 | Fees.
In accordance with section 4104.18 of the Revised Code, the fees related to this section are as follows:
(A) The owner or user of a boiler required under section 4104.12 of the Revised Code to be inspected upon installation, and the owner or user of a boiler for which a certificate of inspection has been issued that is replaced with an appropriate certificate of operation, shall pay to the superintendent of industrial compliance an initial certificate of operation fee in the following amount, as applicable:
(1) One hundred ten dollars for boilers subject to annual inspections under section 4104.11 of the Revised Code;
(2) Two hundred twenty dollars for boilers subject to biennial inspection under section 4104.13 of the Revised Code;
(3) Three hundred thirty dollars for boilers subject to triennial inspection under section 4104.11 of the Revised Code;
(4) Five hundred fifty dollars for boilers subject to quinquennial inspection under section 4104.13 of the Revised Code.
(B) The owner or user of a boiler required under section 4104.12 of the Revised Code to be inspected upon installation, and the owner or user of a boiler for which a certificate of inspection has been issued that is replaced with an appropriate certificate of operation, shall pay to the superintendent of industrial compliance an annual certificate of operation renewal fee in the following amount, as applicable;
(1) One hundred ten dollars for boilers subject to annual inspections under section 4101.11 of the Revised Code;
(2) Two hundred twenty dollars for boilers subject to biennial inspections under section 4104.13 of the Revised Code;
(3) Three hundred thirty dollars for boilers subject to triennial inspections under section 4104.11 of the Revised Code;
(4) Five hundred fifty dollars for boilers subject to quinquennial inspections under section 4104.13 of the Revised Code.
(C) The fee for complete inspection during construction by a general inspector on boilers and pressure vessels manufactured within the state shall be forty-six dollars per hour. Boiler and pressure vessel manufacturers other than those located in the state may secure inspection by a general inspector on work during construction, upon application to the superintendent, and upon payment of a fee of thirty-five dollars per hour, plus the necessary traveling and hotel expenses incurred by the inspector.
(D) The application fee for steam engineer, high pressure boiler operator, or low pressure boiler operator licenses is twenty-five dollars. The fee for each original or renewal steam engineer, high pressure boiler operator, or low pressure boiler operator license is seventy-two dollars.