Rule 1501:9-10-05 | Burial of pipelines.

 

(A) Metallic and nonmetallic pipelines. Excluding all pipelines utilized in the actual drilling or operation of oil and/or natural gas well(s) and pipelines used to transport leasehold gas. No person may lay an oil and/or natural gas pipeline used in the producing of oil and/or natural gas wells that is constructed of metallic or nonmetallic materials unless such pipeline is buried at least twenty-four inches below the ground surface. The owner of such pipeline under this paragraph is exempt from the provisions of this paragraph if the owner finds that:

(1) The land across which the pipeline is to be laid is not reasonably expected to be under cultivation; or

(2) The pipeline can be buried with less than twenty-four inches of cover with minimal risk of safety or environmental damage; or

(3) The topographical features or ground conditions prevent the efficient burial of pipelines; or

(4) The terms of the oil and gas lease prohibit the burial of pipelines or permit surface installation.

(B) Whenever a pipeline is laid in accordance with one or more of the above exemptions, the owner of such pipeline will file a statement with the chief of the division of oil and gas resources management identifying:

(1) Owner's name and address,

(2) The location of the pipeline, and

(3) The exceptions justifying the construction.

Last updated July 1, 2024 at 4:08 AM

Supplemental Information

Authorized By: 1509.03, 1509.23
Amplifies: 1509.03, 1509.23
Five Year Review Date: 10/13/2025
Prior Effective Dates: 4/10/1981, 4/15/2004