Rule 3745-525-315 | Criterion for approval of an application for a permit to install and operate for a CCR unit.

 

The director shall not approve an application for a permit to install and operate for a CCR unit unless the director determines that the CCR unit will be capable of being constructed, operated, closed, and maintained during the post-closure care period in accordance with this chapter, and with the terms and conditions of the permit.

Last updated October 1, 2026 at 9:19 AM

Supplemental Information

Authorized By: 3734.48
Amplifies: 3734.48
Five Year Review Date: 10/1/2031