Section 5525.08 | Disposition of bids of unqualified bidders - nonresponsive bids.
...Except as otherwise provided in this section, the director of transportation shall not consider any bid filed with the director by any person who has not been qualified to bid. Bids from unqualified bidders discovered by the director prior to the reading thereof to be from such persons shall be returned without being read. If the director finds, subsequent to the opening of bids, that facts exist that would disqualif... |
Section 5525.09 | False statement with respect to financial worth.
...No applicant for qualification shall knowingly make a false statement with respect to his financial worth in any application for qualification, financial statement, or other written instrument filed by him with the department of transportation, pursuant to sections 5525.02 to 5525.09 of the Revised Code, or the rules and regulations adopted pursuant thereto. Whoever violates this section shall be disqualified from ... |
Section 5525.10 | Contracts not to be awarded for more than cost plus five per cent.
...f the Revised Code, no contract for any road improvement shall be awarded for a greater sum than the estimated cost thereof plus five per cent. The bids received for an improvement shall be opened at the time and place stated in the notice and the bids shall conform to such other requirements as the director of transportation prescribes. If no acceptable bid is made the director may readvertise the work at the origin... |
Section 5525.11 | Contract upon a unit price basis.
...The director of transportation may enter into any contract authorized by law upon a unit price basis. Where a contract is entered into upon a unit price basis, the contractor shall state in his bid the sum for which he offers to perform each unit of each different kind or class of work, and upon completion the quantities of each kind of work shall be measured and the contractor paid only for the quantities of work ac... |
Section 5525.12 | Lumber deemed material.
...Lumber in highway work shall be deemed material within the meaning of sections 153.54, 1311.26, and 5525.16 of the Revised Code when it actually becomes part of the structure or improvement in which it is used, or when it is used as form material. |
Section 5525.13 | Limitation of surety bond and insurance.
...Where surety bond is accepted from a surety company by the director of transportation on a contract it shall not be for more than ten per cent of the company's capital and surplus, unless the amount in excess of ten per cent is fully reinsured in some surety company that is authorized to transact business in this state. The director may limit the total amount of insurance in force at any one time in any one company.... |
Section 5525.14 | Written change orders or orders for extra work.
...(A) Notwithstanding sections 125.01 to 125.11 of the Revised Code, the director of transportation, by written instruction to the contractor, may increase the quantities of any item specified or not specified in a competitively bid construction contract but, except as provided in division (B) of this section, the additional cost incurred by the increase shall not exceed the lesser of one hundred thousand dollars or fi... |
Section 5525.15 | Cost estimates may be confidential.
... local political subdivisions or to railroad or railway companies proposing to pay any portion of the cost of an improvement. Planning estimates are those estimates created for management of the capital program of the department and are public records for purposes of section 149.43 of the Revised Code. Section 5525.10 of the Revised Code, which provides that no contract for any improvement shall be awarded for ... |
Section 5525.16 | Contract performance bond and payment bond.
...grade separation will indemnify any railroad company involved against any damage that may result by reason of the negligence of the contractor in making the improvement. (2) A payment bond in an amount equal to one hundred per cent of the contract amount, conditioned for the payment by the contractor and all subcontractors for labor or work performed or materials furnished in connection with the work, improvement, ... |
Section 5525.17 | Failure of contractor or surety to complete work.
...If a contractor has not commenced his work within a reasonable time, or does not carry the same forward with reasonable progress, or is improperly performing his work, or has abandoned, or fails or refuses to complete a contract entered into under Chapters 5501., 5503., 5511., 5513., 5515., 5516., 5517., 5519., 5521., 5523., 5525., 5527., 5528., 5529., 5531., 5533., and 5535. of the Revised Code, the director of tran... |
Section 5525.18 | Contract with foreign corporation.
...No contract shall be entered into by the director of transportation, if the bidder awarded the contract is a foreign corporation, until the secretary of state has certified that the corporation is authorized to do business in this state, and, if the bidder awarded the contract is a person or partnership nonresident of the state, until the person or partnership has filed with the secretary of state a power of attorney... |
Section 5525.19 | Payment of costs.
...Payment for the cost of the establishment, construction, reconstruction, improvement, maintenance, and repair of a highway under Chapters 5501., 5503., 5511., 5513., 5515., 5516., 5517., 5519., 5521., 5523., 5525., 5527., 5528., 5529., 5531., 5533., and 5535. of the Revised Code shall be made at intervals of not less than once a month as the work progresses, upon estimates made by the district deputy director of tran... |
Section 5525.20 | Incentive and disincentive contract provisions.
...(A) Subject to division (B) of this section, the director of transportation may include incentive and disincentive provisions in contracts the director executes for projects or portions or phases of projects that involve any of the following: (1) A major bridge out of service; (2) A lengthy detour; (3) Excessive disruption to traffic; (4) A significant impact on public safety; (5) A link that completes a segment... |
Section 5525.21 | Authorizing minimal amount of foreign steel products in bridge projects.
...In conjunction with the requirements of section 153.011 of the Revised Code, the director of transportation may, in connection with any bridge project for which a contract has been entered into, authorize in writing the use of a minimal amount of foreign steel products if either of the following is true: (A) The cost for each contract item used does not exceed one-tenth of one per cent of the total contract cost, or... |
Section 5525.22 | Demolition contracts.
...For contracts for projects that involve the demolition of property for a right-of-way, the director of transportation shall include in the contract adequate provision for liquidated damages and a requirement that the contractor inform the department of the method for disposal of demolition debris prior to the start of work. |
Section 5525.23 | Binding dispute resolution for contract controversies.
...(A) The director of transportation may include in any construction contract a provision authorizing a binding dispute resolution method for any controversy subsequently arising out of the contract. The binding dispute resolution method may proceed only upon agreement of all parties to the controversy. If all parties do not agree to proceed to binding dispute resolution, a party having a claim against the departmen... |
Section 5525.25 | Warranty specifications in bidding documents.
...markings, raised pavement markers, guardrail, and other project items as determined by the director. This section does not apply to contracts the director makes on behalf of a political subdivision. |
Section 5525.99 | Penalty.
...(A) Whoever violates sections 5525.02 to 5525.09, inclusive, of the Revised Code, shall be fined not less than one hundred nor more than five hundred dollars. |
Section 5526.01 | Contracts for professional services definitions.
...As used in this chapter: (A) "Firm" means any person or limited liability company that is legally engaged in rendering professional services. (B) "Federal Water Pollution Control Act" has the same meaning as in section 6111.01 of the Revised Code. (C) "Professional services" means any of the following: (1) The practice of engineering as defined in section 4733.01 of the Revised Code; (2) The practice of surv... |
Section 5526.02 | Contracts for professional services.
...Notwithstanding Chapter 125. and sections 153.65 to 153.71 of the Revised Code, the director of transportation may employ or enter into contracts with any qualified firm for professional services in accordance with this chapter. |
Section 5526.03 | Notice of intent to enter into contract for professional services.
...The director of transportation shall issue public notice of the intent of the department of transportation to enter into a contract for professional services. The director shall advertise the public notice via the internet or by other means to ensure that qualified firms are notified and given the opportunity to be considered for the award of the contract. The director may include more than one contract in a single p... |
Section 5526.04 | Prequalification requirements for firms seeking to provide professional services.
...The director of transportation may institute prequalification requirements for firms seeking to provide professional services and may require that each prequalified firm maintain a current statement of qualifications with the department of transportation. The prequalification requirements shall be based on the factors set forth in division (D) of section 5526.01 of the Revised Code. |
Section 5526.05 | Evaluation of qualifications.
...(A) For every professional service contract for which the department of transportation provides public notice under section 5526.03 of the Revised Code, the director of transportation shall evaluate the qualifications of each firm seeking to enter into the contract with the department. The director may hold discussions with any such firm for the purposes of obtaining more information about a statement of qualificatio... |
Section 5526.06 | Contracts for professional services rules.
...(A) The director of transportation may adopt, amend, or rescind rules in accordance with Chapter 119. of the Revised Code for the purpose of implementing sections 5526.02 to 5526.05 of the Revised Code. (B) Sections 5526.02 to 5526.05 of the Revised Code do not apply to any of the following: (1) A project with an estimated cost of less than fifty thousand dollars; (2) A project that is determined by the director ... |
Section 5526.07 | Professional liability insurance policy.
...(A) Except for any firm providing professional services that relate to research or training, right-of-way acquisition services, or services to assist the department of transportation in the administration of contract claims, a firm that renders professional services to the department, during the period of the performance of professional services for the department and for any other period of time specified in a contr... |