Section 4957.05 | Apportionment of cost.
...he construction of the improvement in a crossing, including the cost of land or property purchased or appropriated, and the payment of damages to abutting property shall be apportioned as follows: (A) The railroad company, or companies if several railroads cross a public way at or near the same point, shall pay, unless otherwise agreed upon, fifteen per cent; (B) The municipal corporation or county shall pay eighty... |
Section 4957.06 | Cost of maintenance of bridge borne by county or state.
...After the completion of the crossing alteration, the crossings and approaches shall be kept in repair as follows: (A) When the public way crosses a railroad, or railroad and interurban railroad, by an overhead bridge, the cost of maintenance must be borne by the county or the state as may be provided by law. (B) When the public way passes under a railroad, or railroad and interurban railroad, the bridge and its abu... |
Section 4957.07 | Assessment and determination of damages.
...All claims for damages by reason of a crossing improvement, filed as provided in section 4957.02 of the Revised Code, shall be assessed and determined as in other cases of public improvements within cities, wherein like claims are made, either before the beginning or after the completion of the proposed crossing improvement, as the legislative authority of the municipal corporation or board of county commissioners de... |
Section 4957.08 | Company failing to comply with agreement.
...eration of its railroad on and over the crossing in question until it complies with the order or decree as is made. |
Section 4957.13 | Court to determine manner of improvement.
...If at the expiration of three months from the passage of the ordinance referred to in section 4957.12 of the Revised Code, the railroad company has refused or failed to co-operate in the preparation of plans and specifications, or if the engineer of the municipal corporation, or engineer designated in such ordinance by the legislative authority of the municipal corporation, and the company fail to agree upon the plan... |
Section 4957.16 | Order of the court.
...ore than one company owns tracks on the crossing in question, the court shall apportion the part of the expenses payable by the companies among such companies. If the court finds that the security and convenience of the public do not require that alterations be made in such crossing, or that none of the plans are reasonable or practicable, the improvement shall not be made upon such plans. Either party feeling aggri... |
Section 4957.17 | Writ of mandamus.
...If a municipal corporation or railroad company refuses or neglects to comply with the orders or findings made by the court as provided in section 4957.16 of the Revised Code, the court may enforce its orders or findings by either mandamus or mandatory injunction, or as for contempt of court, as the necessity of the case requires, upon the application of either party to such proceedings. |
Section 4957.19 | Payment of railroad company's proportion of cost.
...pany of the proportion of the cost of a crossing improvement which the company is required to pay. |
Section 4957.21 | Claims for damages and judicial inquiry.
...The laws relating to the manner of service of the notices, the filing of claims for damages, and the effect of failure to file the claims, shall apply to the notice provided in section 4957.20 of the Revised Code and to all claims for damages by reason of the proposed improvement. After the expiration of the time for the filing of the claims, the legislative authority of the municipal corporation, when claims have be... |
Section 4957.22 | Height of viaduct.
...Any way, crossing, or viaduct constructed over a railroad track in any municipal corporation shall be of such height as not to be of less than twenty-one feet in the clear from the top surface of the rails in the railroad track to the lowest point or projection of such overhead way, crossing, or viaduct, unless the railroad company consents to, or the court of common pleas orders, a less height. In no event shall suc... |
Section 4957.23 | Acquiring land for erection of piers and supports.
...The land or property required to make alteration in the street, road, alley, or other way, or any right, title, or interest in a public street, alley, or other way, required for the erection of piers or supports in any municipal corporation, necessitated by a proposed improvement, shall be purchased or appropriated by the municipal corporation or railroad company in the manner provided for in sections 163.01 to 163.2... |
Section 4957.24 | Cost of maintenance.
...After the completion of the work, crossings and approaches shall be kept in repair as follows: (A) When the public way crosses a railroad by an overhead bridge, the cost of maintenance must be borne by the municipal corporation; (B) When the public way passes under the railroad, the bridge and its abutments shall be kept and maintained by the railroad company, and the public way and its approaches shall be maintain... |
Section 4957.26 | Repairs.
...A street railway company shall keep in repair at its own expense all tracks affected by the improvement referred to by section 4957.25 of the Revised Code and all construction work of whatever character necessary to support such tracks. |
Section 4957.32 | Appeals.
...Appeals may be taken from the decision of the court of common pleas to the court of appeals in proceedings under section 4957.31 of the Revised Code, as in civil actions. The decision of that court shall be final and conclusive. In both the court of common pleas and court of appeals, proceedings brought under this section and section 4957.31 of the Revised Code shall be advanced over other civil causes. |
Section 4957.34 | Plans and specifications to be filed with commission.
...Every railroad company, public or private corporation, or person building, or permitting to be built, any bridge, viaduct, overhead roadway, footbridge, wire, and other structure mentioned in sections 4957.35 and 4957.36 of the Revised Code shall, before proceeding, file with the public utilities commission, plans and specifications for, and have its permit for, the erection of such structure or wire. |
Section 4957.35 | Height of structures over railroads.
...Except cases in which the public utilities commission finds that such construction is impracticable, bridges, viaducts, overhead roadways, footbridges, wire, or other structure built over the track of a railroad after April 16, 1900, by a county, municipal corporation, township, railroad company, or other corporation or person, shall be not less than twenty-one feet in the clear from the top of the rails of such trac... |
Section 4957.36 | Exceptions.
...The exception in section 4957.35 of the Revised Code does not apply to the structures named in such section when built over the main tracks of railroads. In cases in which it is allowed, the public utilities commission shall file in its office a written statement of the facts upon which it relied in finding the required construction impracticable. Such clearances over and adjacent to railroad tracks in terminals may ... |
Section 4957.38 | Injunction.
...Sections 4957.34 to 4957.37, inclusive, of the Revised Code, may be enforced by an injunction on complaint of any interested person, corporation, or board. |
Section 5523.06 | Right to file answer to petition - presentation of other plans - hearing - finding.
...t other plans for the abolition of such crossing. After expiration of such forty days the court shall proceed to a hearing upon the petition and any answers that have been filed, which hearing must be advanced upon the docket upon motion of either party. After examination of all plans presented to it and after hearing the evidence, the court shall make a finding as to whether such plans or any of them are reasonable ... |
Section 5523.07 | Finding of court - modification or alteration of plans - apportionment - appeal.
... more than one company owns tracks on a crossing in question, the court may apportion among them the fifteen per cent or other agreed proportion provided by section 5523.08 of the Revised Code to be paid by such companies, and when making such apportionment the court shall take into consideration the difference in cost of construction and the benefits derived as between companies. If the court finds that none of the ... |
Section 5523.09 | Contract to be approved by attorney general.
...Before the director of transportation may enter into any contract provided for in section 5523.08 of the Revised Code, such contract shall be submitted to and receive the approval of the attorney general as to its form. |
Section 5523.14 | Clearance under viaduct.
...Any way, crossing, or viaduct constructed over the tracks of any railroad company under sections 5523.01 to 5523.13, inclusive, of the Revised Code, shall be of such height as not to be less than twenty-one feet in the clear, from the top surface of the rails of the railroad track to the lowest point or projection of such overhead way, crossing, or viaduct, unless such company consents to or the court orders a less h... |
Section 5523.16 | Appeal to public utilities commission.
...From the finding and order of the director of transportation that such improvement as provided for in section 5523.02 of the Revised Code is reasonably necessary and expedient, any railroad company or any interurban railway company may, upon the question of such necessity and expediency, take an appeal to the public utilities commission. A party desiring to take an appeal shall file with the director written notice o... |
Section 5523.17 | Improvement to be kept in repair - responsibility for bridge inspection.
...ng, widening, or realigning a separated crossing by the director of transportation, in accordance with sections 5523.01 to 5523.20 of the Revised Code, the separated crossing and approaches thereto shall be kept in repair as follows: (A) When the public way crosses the tracks of any railroad company by a structure carrying the highway over such tracks the responsibility for inspection and the cost of maintenance sha... |
Section 5561.05 | Hearing - finding - appeal.
...t other plans for the abolition of such crossing. After the expiration of such period the court of common pleas shall proceed to a hearing upon the petition and any answers that have been filed, which hearing must be advanced upon the docket upon motion of either party. After examination of all plans presented to it and after hearing the evidence, the court shall make a finding as to whether such plans or any of them... |