Rule 3745-52-260 | Purpose and implementation of contingency plan - preparedness, prevention, and emergency procedures for large quantity generators.

 

(A) A large quantity generator shall have a contingency plan for the facility. The contingency plan shall be designed to minimize hazards to human health or the environment from fires, explosions, or any unplanned sudden or non-sudden release of hazardous waste or hazardous waste constituents to air, soil, or surface water.

(B) The provisions of the contingency plan shall be carried out immediately whenever there is a fire, explosion, or release of hazardous waste or hazardous waste constituents which could threaten human health or the environment.

Supplemental Information

Authorized By: 3734.12
Amplifies: 3734.12
Five Year Review Date: