Rule 4906-4-02 | Project summary and applicant information.

 

The applicant shall provide a summary of the proposed project consistent with that presented at public informational meetings. The summary should be suitable as a reference for state and local governments and for the public. Examples of relevant information for inclusion in the project summary are:

(A) A statement explaining the purpose of the facility.

(B) A description of the location, size, acreage, and operating characteristics of the proposed facility.

(C) A discussion of the suitability of the site or route for the proposed facility.

(D) A description of the applicant's history, affiliate relationships, and current operations, and a description of the entity that will construct and operate the facility, if different from the applicant.

(E) For a proposed electric generation facility, a description of any plans for future additions of electric power generation units for the site and region (including the type and timing) and the capacity anticipated for the site.

Last updated May 30, 2024 at 9:14 AM

Supplemental Information

Authorized By: 4906.03, 4906.20
Amplifies: 4906.03, 4906.04, 4906.06, 4906.10, 4906.13, 4906.20
Five Year Review Date: 5/20/2029
Prior Effective Dates: 12/27/1976, 7/7/1980, 8/28/1998, 12/15/2003, 1/25/2009, 5/7/2009, 12/11/2015