Section 3318.083 | Sharing of approved increase in basic project cost.

 
You are viewing a past version of this section that is no longer in effect View Current Version

If, after the Ohio school facilities commission and a school district enter into a written agreement under section 3318.08 of the Revised Code for the construction of a classroom facilities project, the commission approves an increase in the basic project cost above the amount budgeted plus any interest earned and available in the project construction fund, the state and the school district shall share the increased cost in proportion to their respective contributions to the district's project construction fund.

Available Versions of this Section