Section 4928.1410
If an electric distribution utility has an existing electric security plan under which the commission had authorized the creation or continuation of riders, then, to the extent those riders will cease to exist after termination of the electric security plan, the electric distribution utility is authorized to create necessary regulatory assets or liabilities, along with carrying costs at the utility's weighted average cost of debt, for the resolution of any outstanding under-collection or over-collection of funds under such riders. The resolution of such regulatory assets or liabilities shall be addressed in the first distribution rate case under section 4909.18 of the Revised Code that occurs after the plan's expiration.
Last updated May 22, 2025 at 12:48 PM
Available Versions of this Section
- August 14, 2025 – Enacted by House Bill 15 - 136th General Assembly [ View August 14, 2025 Version ]