Section 5555.61 | Contract for improvement not to exceed ten per cent above estimates.
Effective:
October 3, 2023
Latest Legislation:
House Bill 33 - 135th General Assembly
After the board of county commissioners decides to proceed with the improvement, it shall do so in accordance with sections 307.86 to 307.92 of the Revised Code. No contract for any improvement shall be awarded at a price more than twenty per cent in excess of the estimated cost.
Last updated September 28, 2023 at 4:11 PM
Available Versions of this Section
- September 27, 1972 – House Bill 1047 - 109th General Assembly [ View September 27, 1972 Version ]
- October 3, 2023 – Amended by House Bill 33 - 135th General Assembly [ View October 3, 2023 Version ]