Rule 4906-3-02 | Preapplication conference.

 

An applicant considering construction of a major utility facility or economically significant wind farm may request a preapplication meeting with the board staff prior to submitting an application. The results of such meeting(s) in no way constitutes approval or disapproval of a particular site or route, and in no way predetermines the board's decision regarding subsequent certification or approval.

Last updated May 30, 2024 at 9:10 AM

Supplemental Information

Authorized By: 4906.03, 4906.20
Amplifies: 4906.03, 4906.04, 4906.06, 4906.10, 4906.13, 4906.20
Five Year Review Date: 5/20/2029
Prior Effective Dates: 12/27/1976, 6/10/1989, 8/28/1998, 12/15/2003, 1/25/2009, 5/7/2009, 12/11/2015