Rule 4906-6-03 | Filing of an accelerated application.
(A) A letter of notification application is due not less than ninety days before the planned commencement of construction. A letter of notification for which the applicant requests expedited processing shall be filed not less than twenty-eight days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-eight day requirement.
(B) Except as described in paragraphs (C) and (D) of this rule, a construction notice is due not less than ninety days before planned commencement of construction. A construction notice for which the applicant requests expedited processing shall be filed not less than twenty-one days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-one day requirement.
(C) A construction notice and any application fee are due not less than sixty days before planned commencement of construction of a major utility facility that meets the site control criteria described in division (H) of section 4906.03 of the Revised Code.
(D) A construction notice for a major utility facility to be located in a priority investment area as described in division (G) of section 4906.03 of the Revised Code shall be considered as follows:
(1) The chairperson shall review the application to determine its completeness as provided in paragraph (A) of rule 4906-3-06 of the Administrative Code.
(2) For projects that are deemed complete, the application shall be considered approved by operation of law unless the board renders a decision concerning the application within 45 days of the completeness determination.