Skip to main content
Back To Top Top Back To Top
The Legislative Service Commission staff updates the Revised Code on an ongoing basis, as it completes its act review of enacted legislation. Updates may be slower during some times of the year, depending on the volume of enacted legislation.

Section 3710.07 | Contractor's duties prior to engaging in project.

 
You are viewing a past version of this section that is no longer in effect View Current Version

(A) Prior to engaging in any asbestos hazard abatement project, an asbestos hazard abatement contractor shall do all of the following:

(1) Prepare a written respiratory protection program as defined by the director of health pursuant to rule, and make the program available to the department of health, and workers at the job site if the contractor is a public entity or prepare a written respiratory protection program, consistent with 29 C.F.R. 1910.134 and make the program available to the department, and workers at the job site if the contractor is a business entity;

(2) Ensure that each worker who will be involved in any asbestos hazard abatement project has been examined within the preceding year and has been declared by a physician to be physically capable of working while wearing a respirator;

(3) Ensure that each of the contractor's employees or agents who will come in contact with asbestos-containing materials or will be responsible for an asbestos hazard abatement project receives the appropriate certification or licensure required by this chapter and the following training:

(a) An initial course approved by the department pursuant to section 3710.10 of the Revised Code, completed before engaging in any asbestos hazard abatement project; and

(b) An annual review course approved by the department pursuant to section 3710.10 of the Revised Code.

(B) After obtaining or renewing a license, an asbestos hazard abatement contractor shall notify the department, on a form approved by the director of health, at least ten days before beginning each asbestos hazard abatement project conducted during the term of the contractor's license.

(C) In addition to any other fee imposed under this chapter, an asbestos hazard abatement contractor shall pay, at the time of providing notice under division (B) of this section, the department a fee of sixty-five dollars for each asbestos hazard abatement project conducted.

Available Versions of this Section