Section 4928.542 | Winning bids; requirements.

 

The winning bid or bids selected through the competitive procurement process established under section 4928.54 of the Revised Code shall meet all of the following requirements:

(A) Be designed to provide reliable competitive retail electric service to percentage of income payment plan program customers;

(B) Reduce the cost of the percentage of income payment plan program relative to the otherwise applicable standard service offer established under sections 4928.141, 4928.142, and 4928.143 of the Revised Code;

(C) Result in the best value for persons paying the universal service rider under section 4928.52 of the Revised Code.